Central Corridor Construction Update

Fourth Street in downtown St. Paul is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Photo courtesy of Met Council

Fourth Street in downtown St. Paul has reopened to traffic after crews substantially completed utility relocation and road construction the day before Thanksgiving. In [...]

Gateway Corridor Trip to Washington,D.C.

Ramsey and Washington County leaders traveled to Washington,D.C.,earlier this month to meet with Congressional representatives and staffers. The topic of discussion was the Gateway transit corridor along Interstate 94 between St. Paul and Wisconsin.

Utility Relocation to begin east of Capitol after July Fourth

This is example of electrical manhole construction,which will be built in University Avenue east of Robert Street and on 12th Street between Cedar and Robert streets starting on or after July 8. Photo courtesy of the Metropolitan Council.

Shortly after July Fourth,utility relocation will begin east of the state Capitol on Robert [...]

Central Corridor Progress Report

Construction bids for the eastern portion of the Central Corridor Light Rail Transit project — the work at the St. Paul end of the line — will be opened May 18,and the Met Council is to award the contract June 23. As previously announced,construction will begin in August east of [...]